A Development Servicing Plan for Water Supply and a Development Servicing Plan for Sewerage have been prepared by Tamworth Regional Council to detail the developer charges to be levied on development areas utilising Council’s water supply and sewerage infrastructure.
Download Development Servicing Plan for Water Supply
Download Development Servicing Plan for Sewerage
Table Disclosing Cross-Subsidy from the Typical Residential Bill
(As required under the Department of Primary Industries “2016 Developer Charges Guidelines for Water Supply, Sewerage and Stormwater”)
Water Service Area
|
Water Supply
|
Sewerage
|
Calculated Maximum Developer Charge
|
Adopted Charge
|
Calculated Maximum Developer Charge
|
Adopted Charge
|
Tamworth
|
$3,768
|
$3,768
|
$1,512
|
$1,512
|
Hills Plain - Gravity Sewer Area
|
$18,973
|
$11,176
|
$14,020
|
$4,349
|
Hills Plain - Pressure Sewer Area
|
$18,973
|
$11,176
|
$6,001
|
$2,033
|
Arcadia
|
$8,501
|
$8,501
|
$6,001
|
$6,001
|
Manilla
|
$3,768
|
$500
|
$6,001
|
$500
|
Barraba
|
$8,501
|
$500
|
$33,999
|
$500
|
Kootingal
(now part of Tamworth Water Supply System)
|
$3,768
|
$3,768
|
$14,020
|
$500
|
Moonbi
(now part of Tamworth Water Supply System)
|
$3,768
|
$3,768
|
no sewer
|
no sewer
|
Nundle
|
$8,501
|
$500
|
no sewer
|
no sewer
|
Attunga
|
$18,973
|
$500
|
no sewer
|
no sewer
|
Bendemeer
|
$28,608
|
$500
|
no sewer
|
no sewer
|
Cross-subsidy from
Annual Water/Sewer Bills
to Developer Charge
|
$0
|
$21.42
|
$0
|
$23.14
|
Total Annual Cross-subsidy
|
$0
|
$831,000
|
$0
|
$849,000
|